Chelsea Court
Equans has successfully been appointed as main contractor to undertake major regeneration works at Chelsea Court.
As per Peabody's requirements, Equans is undertaking internal remodelling of the block and complete refurbishment of the 71 self-contained flats with new communal facilities, main entrance, fire escape link bridge, vehicle and pedestrian entrance, terrace, landscaping and new roof.
We are also renewing internal elements including doors, kitchens, bathrooms, ceilings, flooring, mechanical, heating, water supply, electrical, lifts, fire alarms, emergency lighting, fire compartmentation, care alarm and door entry IRS/4G system as well as a new Mechanical Ventilation Heat Recovery (MVHR) system.
The scheme is split into three phases; Phase 1 includes works to the West Wing, Phase 2 to the East Wing and finally Phase 3 to the North Wing.
The scheme is expected to be completed by Summer 2024.
Equans has successfully been appointed as main contractor to undertake major regeneration works at Chelsea Court.
As per Peabody's requirements, Equans is undertaking internal remodelling of the block and complete refurbishment of the 71 self-contained flats with new communal facilities, main entrance, fire escape link bridge, vehicle and pedestrian entrance, terrace, landscaping and new roof.
We are also renewing internal elements including doors, kitchens, bathrooms, ceilings, flooring, mechanical, heating, water supply, electrical, lifts, fire alarms, emergency lighting, fire compartmentation, care alarm and door entry IRS/4G system as well as a new Mechanical Ventilation Heat Recovery (MVHR) system.
The scheme is split into three phases; Phase 1 includes works to the West Wing, Phase 2 to the East Wing and finally Phase 3 to the North Wing.
The scheme is expected to be completed by Summer 2024.
-
Site achieves National Considerate Constructors Scheme Award
We are thrilled to announce that the Chelsea Court scheme has received a 2024 National CCS Award.
This award is a real testament to the site team's approach and how they deliver the works, with a genuine commitment to having a positive impact in the communities where they operate.
Regeneration Director for Equans, Barry McCarthy commented: "Visit after visit, the delivery team involved received excellent CCS scores (including four consecutive 45/45 results), setting and raising the bar in our industry for what considerate construction looks like - you should all be extremely proud to be recognised with this exceptional accolade. Well done and thank you."
The CCS' national award scheme has been rewarding the UK’s most considerate sites since 1998 when they launched the National Site Awards. Today like then, the Awards are one of the most recognised construction industry awards in the sector and represent an exceptional accolade that recognises the sites that have made the greatest contribution towards improving the image of construction.
Divisional Manager, James Jennings said: "The consistent high scores are a testament to site team members past and present. Stephen Smith has been a constant throughout these scores being achieved and has developed those working with him to bring them up to his expected high standards. It's an absolute pleasure working with Stephen and I'm pleased that his and the teams hard work and dedication is being recognised."
-
Works update - February 2024
Welcome to our site works update for February
February has seen the continuation of progress with the ongoing installation of ventilation ducting and sprinkler systems throughout the east wing.
Structural surveys and investigations in the north wing have continued, the removal of scaffolding to the riverside elevation has now been completely removed.
The continuation of M&E aspects including ceilings and walls being installed on the east wing is being progressed along with the completion of riser reinforcement. Preparation for the MVHR plant has started within the loft space along with the new insulation and boarding.
We apologise for any inconveniences arising from our works.
Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.
What to expect in March:
East wing:
- Continuation of wall and ceiling installations
- Completion of M&E installations to remaining risers and flats
New lobby entrance:
- Commencement of landscaping, ground works and masonry package
- Structural steel frame construction
North wing:
- Continued design related planning and surveys
If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.
To view the full resident newsletter for February, please click here.
-
Works update - January 2024
Welcome to our site works update for January
Happy new year from Equans!
We're back with our January update.
January will see the continuation of progress throughout the east and west wing. New electric meters are continuing to be connected and fitted in the basement ready for the new supply to be connected.
Structural surveys and investigations in the north wing are fully underway, the removal of scaffolding to the riverside elevation has now been completely removed.
The continuation of M&E aspects including ceilings and walls being installed on the east wing is being progressed along with the completion of riser reinforcement. We apologise for any inconvenience arising from our works.
Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.
What to expect in February:
East wing:
- Continuation of wall and ceiling installations
- Completion of M&E installations to remaining risers and flats
New lobby entrance:
- Internal finishes and new entrance door installations
- Commencement of landscaping, ground works and masonry package
- Structural steel frame construction
North wing:
- Continued design related planning and surveys
If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.
To view the full resident newsletter for January, please click here.
-
Works update - December 2023
Welcome to our site works update for December
As we head towards the Christmas period December has brought integral progress throughout the East and West wing. New electric meters are fitted in the basement ready for the new supply to be connected, along with careful design planning of the North wing and the removal of scaffolding externally means progression is at full speed.
The continuation of M&S including ceilings and walls being installed on the East wing also keeps us on programme and looking good for the new year.
Equans would like to wish you all a Merry Christmas and a Happy New Year and we apologise for any inconveniences arising from our works.
Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.
What to expect in December:
East wing:
- Scaffold removal completion (Riverside)
- Continuation of wall and ceiling installations
- M&E installations to remaining risers and flats
New lobby entrance:
- Preparation for internal finishes and new entrance doors
- Preparation for completion of landscaping, ground works and masonry package
North wing:
- Continued design related planning
If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.
To view the full resident newsletter for December, please click here.
-
Works update - November 2023
Welcome to our site works update for November
As we head towards the Christmas period November has been fruitful in progress throughout the East wing, with the removal of scaffold externally and the progression of M&E including ceilings and walls being installed. The development of the new lobby entrance has also progressed well.
All structural openings in the lobby area have now been installed allowing internal works to be programmed.
The completion of designs for the North wing is well underway ensuring potential future complications are addressed appropriately.
Tree pruning has also been completed on the roadside perimeter of the block.
Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.
What to expect in December:
East wing:
- Scaffold removal completion
- Continuation of wall and ceiling installations
- M&E installations to remaining risers and flats
- Reinforcement to enlarged risers
New lobby entrance:
- Preparation for internal finishes and new entrance doors
- Preparation for completion of landscaping, ground works and masonry package
If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.
To view the full resident newsletter for November, please click here.
-
Changes to the site team
Please join us us welcoming Senior Site Manager, Matthew Littman to the Chelsea Court site team.
Matthew joins the team as a replacement for Sergiu who has now left the scheme. Please direct any queries or concerns you may have about the works to Matthew - his contact details can be found under the 'Contact Us' section.
-
Happy Halloween from Equans
From all of us at Equans, we wish you a happy Halloween.
A children's activity pack can be viewed and downloaded from our 'Documents Library'.
Please be careful if carving pumpkins and stay safe whilst trick or treating.
-
Works update - October 2023
Welcome to our site works update for October
October has seen great progress for the development of the new entrance at Chelsea Court.
We have completed the new roof over the central core and soon after the ceiling install, the scaffold will be removed from the 5th floor.
New AOV windows will be part of the fire passive protection of the building.
We are about to complete the temporary works for new door openings including the new patio door.
For the east wing, a positive continuation of all tasks is underway with first fix works being carried out over many different trades and new partition walls started from the 5th floor down.
The chimney opening on the 3rd floor - one of the most complex tasks for the east wing, is booked for the second part of October.
North wing open investigations are currently in progress and will be complete by the end of October.
Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.
What to expect in November
- Continuation of first fix works to all floors on the east wing
- Build up partition walls as the new flats take shape
- West wing ground floor continuation with bigger progress on the new entrance and landscape works
- Scaffolding is due to be struck in the first half of November, on the street side of the building
- Tree pruning will take place to remove the parts affected by disease
If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.
To view the full resident newsletter for October, please click here.
-
Fourth consecutive top score from Considerate Constructors Scheme for Chelsea Court team
The team at Chelsea Court have, for the fourth consecutive time, once again achieved an impressive top score of 45/45 from their recent audit visit by the Considerate Constructors Scheme (CCS).
Upon hearing the news Divisional Manager, James Jennings commented: "This is an amazing achievement by all involved but a special mention for Stephen Smith our Project Manager, a very focused and meticulous Manager that I really appreciate and enjoy working with."
When the CCS monitor visited the scheme earlier this month to carry out their audit of the site, they commented things like "This is an excellent project which is demonstrating robust commitment to the CCS Code of Considerate Practice. Emphasis is placed on consideration for the elderly residents and the site team strive to ensure that there is minimal disruption whilst the works are in progress. The extensive landscaping within the communal garden will leave a positive environmental legacy well after the works are completed."
The CCS is an independent organisation founded to raise standards in the construction industry to ensure all construction sites present an image of competent management, efficiency, awareness of environmental issues and above all neighbourliness. Monitors from the scheme regularly audit our sites to ensure we are adhering to the scheme’s Code of Considerate Practice which is designed to encourage best practice beyond statutory requirement.
Each audit is split into three categories; respect for the community, protecting the environment and valuing the workforce each with a potential score out of 15 with a total combined max score of 45 available. To score above 13 in any category warrants an excellent level of achievement for that category.
Congratulations to Site Managers, Sergiu and Adie and the rest of the site team, who work so hard every day to maintain such high standards
-
Works update - August 2023
Welcome to our site works update for August
August has seen great strides for the development of the new communal garden at Chelsea Court, this includes all current work streams related to the external envelope that being the new drainage system, car park and pedestrian setting out and progresses on the ground floor to the new entrance.
For the east wing a positive continuation of all work streams is underway with first fix being carried out over many different trades.
North wing will soon have minor investigation works to aid finalisation of the design queries.
What to expect in September
- North wing investigation works
- Continuation of first fix on east wing - all floors
- Landscape and new entrance progress
If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.
To view the full resident newsletter for August, please click here.
Contact Us
-
Phone 0800 022 4040 Email customercareline@peabody.org.uk -
Phone 07583011562 Email matthew.littman@equans.com -
Phone 07814069510 Email stephen.smith@equans.com
Documents
-
Resident Newsletters
- Resident Newsletter_Feb24 (771 KB) (pdf)
- Resident Newsletter_Jan24 (695 KB) (pdf)
- Resident Newsletter_Dec23 (754 KB) (pdf)
- Resident Newsletter_Nov23 (462 KB) (pdf)
- Resident Newsletter_Oct23 (444 KB) (pdf)
- Resident Newsletter_Aug23 (437 KB) (pdf)
- Resident Newsletter_Jul23 (305 KB) (pdf)
- Resident Newsletter_Jun23 (433 KB) (pdf)
- Resident Newsletter_May23 (346 KB) (pdf)
- Resident Newsletter_MarApr23 (413 KB) (pdf)
- Resident Newsletter_Feb23 (365 KB) (pdf)
- Resident Newsletter_Jan23 (131 KB) (pdf)
- Resident Newsletter_Dec22 (449 KB) (pdf)
- Resident Newsletter_Oct22 (346 KB) (pdf)
- Resident Newsletter_Sep22 (264 KB) (pdf)
- Resident Newsletter_Aug22 (210 KB) (pdf)
- Resident Newsletter_Jul22 (292 KB) (pdf)
- Resident Newsletter_Jun22 (568 KB) (pdf)
- Resident Newsletter_May22 (614 KB) (pdf)
- Resident Newsletter_Feb22 (822 KB) (pdf)
- Resident Newsletter_Dec21 (1.49 MB) (pdf)
- Resident Newsletter_Sep21 (1.79 MB) (pdf)
- Resident Newsletter_Apr21 (2.16 MB) (pdf)
- Resident Newsletter_Mar21 (2.09 MB) (pdf)
- Resident Newsletter_Feb21 (1.96 MB) (pdf)
- Resident Newsletter_Jan21 (2.84 MB) (pdf)
- Fire Safety Guidance Documents
- Halloween Activity Pack_Oct22 (990 KB) (pdf)
- Home User Guide (1.16 MB) (pdf)