Works update - February 2024

Welcome to our site works update for February

February has seen the continuation of progress with the ongoing installation of ventilation ducting and sprinkler systems throughout the east wing.

Structural surveys and investigations in the north wing have continued, the removal of scaffolding to the riverside elevation has now been completely removed.

The continuation of M&E aspects including ceilings and walls being installed on the east wing is being progressed along with the completion of riser reinforcement. Preparation for the MVHR plant has started within the loft space along with the new insulation and boarding.

We apologise for any inconveniences arising from our works.

Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

What to expect in March:

East wing:

  • Continuation of wall and ceiling installations
  • Completion of M&E installations to remaining risers and flats

New lobby entrance:

  • Commencement of landscaping, ground works and masonry package
  • Structural steel frame construction

North wing:

  • Continued design related planning and surveys

If you have any queries about the works being carried out please speak to Senior Site Manager, Matthew on 07583 011 562.


To view the full resident newsletter for February, please click here.