Green Lanes, Haringey

Green Lanes, Haringey is a new development being built in partnership with Clarion Housing Group.

The scheme includes 133 new homes across 6 blocks, ranging from 4 – 7 storeys, a new NHS facility and a new energy centre to power the new development.

The project will begin at the end of August, and is due to complete in Autumn of 2021.

This website will keep everyone updated on the progress of the development - and if you have any questions, please see the contact us section.


Green Lanes, Haringey is a new development being built in partnership with Clarion Housing Group.

The scheme includes 133 new homes across 6 blocks, ranging from 4 – 7 storeys, a new NHS facility and a new energy centre to power the new development.

The project will begin at the end of August, and is due to complete in Autumn of 2021.

This website will keep everyone updated on the progress of the development - and if you have any questions, please see the contact us section.


  • Site update: November 2020

    supporting image

    The external envelope to five blocks are well underway and progressing toward the roofs. Waterproofing works to the roof and terrace areas are complete to three blocks with the two remaining blocks nearing completion. Internal works are progressing well with the individual flat fitout moving on.

    The next milestone will be the commencement of the UKPN, which we are hoping to start prior to the Christmas break. This is the completion of all the cabling works from the existing UKPN substation into the newly formed energy centre, which will provide services to the new development as well as provide power to the surrounding properties.

  • Site update: October 2020

    supporting image

    We are making great progress on site; the new Energy Centre is now fully complete, and all equipment has been installed. It is now just awaiting the electrical connection from UKPN to bring it fully on-line.

    Block A is now fully scaffolded and enclosed with monarflex. External walls now have metsec and windows and the external brickwork is progressing. The roof and terraces are now fully waterproofed, and we started to form internal walls for all of the individual flats and corridors.

    The external walls, windows and brickwork in Blocks B-E are progressing beyond the 1st floors. The roof and terraces are being waterproofed, and we have also we started to form internal walls for the individual flats.

    Block F is currently awaiting the removal of the existing substation before we can commence the frame. At present this has been re-programmed to commence at the beginning of 2021.


  • Site update - Q1 2020

    supporting image

    We have completed all the excavation and piling works across all blocks. The concrete frame is progressing well along with installing underground services and drainage. Block A is currently up to the first floor, Block B and C are at the third floor whereas Block D and E at ground floor level.

    We will shortly be progressing the new energy centre which will be responsible for powering the new development.

    The next phase of works will see scaffolding, metsec and brickwork all commence on the main blocks.

    We have recently revamped our site hoarding and site entrances and installed signage across the project. All the relevant contact details for the ENGIE site team can be found clearly displayed. Please feel free to contact us if you have any queries or concerns
  • What's happening over the next few months

    Starting from the end of August, we will be performing site enabling works and site establishment.

    Next steps will be piling for blocks A, B, C and the energy centre. We will then begin the concrete frame, as well as ground works and drainage.

    As we progress, we will upload photos and updates. However if you have any questions, please feel free to get in touch via the contact us section.

Page last updated: 15 Aug 2019, 02:29 PM