Site update - Q1 2020

We have completed all the excavation and piling works across all blocks. The concrete frame is progressing well along with installing underground services and drainage. Block A is currently up to the first floor, Block B and C are at the third floor whereas Block D and E at ground floor level.

We will shortly be progressing the new energy centre which will be responsible for powering the new development.

The next phase of works will see scaffolding, metsec and brickwork all commence on the main blocks.

We have recently revamped our site hoarding and site entrances and installed signage across the project. All the relevant contact details for the ENGIE site team can be found clearly displayed. Please feel free to contact us if you have any queries or concerns
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>