Flamingo Court



Welcome to the microsite for Flamingo Court, London. This site will provide regular updates on works being undertaken on your building, house documents that are sent out to you and provide clear information on what to expect.

Starting from July 2021, ENGIE will be undertaking fire safety and fire prevention on behalf of Optivo. The works to be undertaken include removal of external wall insulation, install cavity wall insulation, install A1 rated external wall insulation, undertake fire remedial works and replacement of windows.



ENGIE will be carrying out the remediation works to your building.

However, you’ll need to contact your landlord, Optivo, if you’ve questions which are not related to the works being carried out.



There are a number of ways you can get in touch with them: www.optivo.org.uk/contactus



You’ll also find further information on their website about this subject: www.optivo.org.uk/firesafety



Welcome to the microsite for Flamingo Court, London. This site will provide regular updates on works being undertaken on your building, house documents that are sent out to you and provide clear information on what to expect.

Starting from July 2021, ENGIE will be undertaking fire safety and fire prevention on behalf of Optivo. The works to be undertaken include removal of external wall insulation, install cavity wall insulation, install A1 rated external wall insulation, undertake fire remedial works and replacement of windows.



ENGIE will be carrying out the remediation works to your building.

However, you’ll need to contact your landlord, Optivo, if you’ve questions which are not related to the works being carried out.



There are a number of ways you can get in touch with them: www.optivo.org.uk/contactus



You’ll also find further information on their website about this subject: www.optivo.org.uk/firesafety

  • Keeping In Contact

    Throughout the work your Resident Liaison Officer (RLO) will be your first point of call for any queries or concerns that you may have. If you are in any doubt about the identity of any people on site, please do not let them into your home. Contact your RLO to check they are who they say they are.

    Nepa Begum - Resident Liaison Officer

    07866 058784

    nepa.begum@engie.com


    Paolo Merrifield - Site Manager

    07811 712193

    paolo.merrifield@engie.com

    Our site staff are available Monday to Friday, 8am to 5pm unless otherwise agreed.

    In an out of hours emergency, please call 07811 712193

    PLEASE NOTE THAT THE CALL OUT NUMBER SHOULD ONLY BE USED AFTER 5PM MONDAY TO FRIDAY AND OVER THE WEEKEND IF YOU HAVE AN ISSUE THAT CANNOT WAIT UNTIL THE FOLLOWING DAY. IF YOU HAVE ANY ISSUES BETWEEN 8AM AND 5PM MONDAY TO FRIDAY PLEASE CONTACT A MEMBER OF THE SITE TEAM ON THE NUMBERS ABOVE.

  • FAQs

    Question - How we will protect the property from the rain & what will happen if property gets damaged?

    Answer

    • Building will be protected from the rain by using fire rated Monarflex where required.
    • Any damage caused to residents’ homes will be rectified without cost to the resident.


    Question – How will dust be controlled as I have open windows?

    • Dust extraction tools will be used; we will communicate with you around any special requirements that you have.


    Comment – Noise in the block really travels around it, please beware.

    • Response – We will be carrying out noisy works & will liaise with you regularly.


    Question - Do I have to let you know if I’m going away.

    • Answer – Yes please, please inform Nepa as resident profiling stage.


    Question - A requirement of the BSF states that scaffolding must be well underway by the end of September to secure the fund, is this on track?

    • Answer – Yes, there is no problem with the BSF reported for this block & scaffolding is well underway.

    Question - Is there an update of the Waking Watch?

    • Answer – ENGIE are working towards providing this service for Optivo in the near future which will be done with a handover from the existing


    Question – Is the OOH’s covered by another builder as there has been problems reported elsewhere?

    • Answer – The OOH’s is ENGIE.


    Question - How will we manage drafts & heat loss?

    • Answer – We will strip the render to reveal any issues in the building face & repair, then install insulation to reduce heat loss. We will also supply oil filled radiators if residents require them for use.


    Question – How will you deal with works on balconies if lots of items on them?

    • Answer – Balconies will need to be cleared to carry out the works, we will liaise with resident on an individual basis.
  • Hello from the ENGIE team!

    We're pleased to have now completed the initial site set up including the heras fencing and staff welfare facilities and are moving forward to the main Construction Phase.

    From mid August to early September, we will be erecting the scaffolding, starting with the front elevation of the building, before moving on to erecting the gantry, hoist and resident respite facilities.

Page published: 21 September 2021, 13:22