Works update - Yorkshire Team - August 2023

We're pleased to provide an overview and update for the works currently being delivered by our Yorkshire team.

If you have any queries or concerns about the works being undertaken by Equans, please contact your appointed Resident Liaison Officer.


Scope of works being delivered:

  • Windows and doors
  • Re-pointing and lintel repairs

Impact from works:

  • Improved ventilation
  • Less heat loss
  • Nosie reduction
  • Reduction of condensation, mould and damp

Project progress:

79 properties completed vs 70 planned. Completion is on target for 31st March 2023 (but sufficient works to run to December 2024).

Completed social value initiatives:

  • Specialise qualification sponsorship - £442.54
  • Financial contribution towards digital devices - £1,500
  • Refurbishment/Improvement - £596.62 Skip Day & £750 Car Park lining
  • Clarion Futures donation - £1,200
  • Contractor engagement - Two Meet the Contractor events
  • Provision of equipment or services - £1,500

Planned social value initiatives:

  • Apprenticeship & job starts: Will be difficult to achieve in this within our current contract but we are actively sharing employment opportunities for job starts with Clarion on a monthly basis
  • Sponsorships & donations: Target achieved
  • Employment, Training & Work Experience: 'Skill for Success' training offered, awaiting Clarion approval
  • Refurbishment projects - In discussion with Clarion regarding Bradford proposal for play area/muga and ginnels
  • School engagement: Awaiting Clarion approval - aiming for first visit in September
  • Staff volunteering: 'Skill for Success' training - awaiting Clarion approval