Works update - October 2022

Welcome to our site works update for October

Site update

Relocation of residents from both the north and east wings has been completed. Those that remained in the east wing have been relocated to the north wing in preparation for phase 2 of the works.

Access to the east wing will now be restricted to the residents.

Current works

The east wing is currently being surveyed. Services are being isolated i.e. water, heating, and electricity are being shut off.

Remedial work

As a reminder for those living in the west wing, please note any works you would like the handyman to carry out in your apartment. The handyman will perform tasks such as mounting shelves, blinds, TVs, coat hooks, picture frames, and assembling flat-pack furniture etc. Please then pass your list to Peabody's Scheme Manager, Alex to be communicated to the site team.

Further update

Scaffolding has been erected around the west wing due to a leak. Alex will be in contact with the residents affected.

If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.