Works update - November 2023

Welcome to our site works update for November

As we head towards the Christmas period November has been fruitful in progress throughout the East wing, with the removal of scaffold externally and the progression of M&E including ceilings and walls being installed. The development of the new lobby entrance has also progressed well.

All structural openings in the lobby area have now been installed allowing internal works to be programmed.

The completion of designs for the North wing is well underway ensuring potential future complications are addressed appropriately.

Tree pruning has also been completed on the roadside perimeter of the block.

Remedial works: Equans is keen to fix any issue with the installation in your new homes. In terms of doing this smoothly, please contact Alex Da Costa, your Scheme Manager as your first point of contact - he will then raise any issues with us.

What to expect in December:

East wing:

  • Scaffold removal completion
  • Continuation of wall and ceiling installations
  • M&E installations to remaining risers and flats
  • Reinforcement to enlarged risers

New lobby entrance:

  • Preparation for internal finishes and new entrance doors
  • Preparation for completion of landscaping, ground works and masonry package

If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.


To view the full resident newsletter for November, please click here.