Works update - May 2023

Welcome to our site works update for May

May has seen good progress in all elements of works on site, firstly with the structural foundation of the new entrance and the first fix carpentry on the east wing.

For the new entrance this has now allowed us to enable the process of the steel framework design and build which takes us from basement to ground level. The east wing has seen great strides, with mechanical, electrical and carpentry first fix currently underway and the new floors being laid.

What to expect in June

  • Steel framework build up
  • Drainage system to new entrance
  • Continuation of first fix on east wing all floors
  • Kitchen fit out for west ground floor communal
  • Continued roof works to east wing

If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.


Please click here to view the latest resident newsletter in full.