Works update - June 2023

Welcome to our site works update for June

June is a month of good progress in all areas of work on site, this includes the installation of the first phase of the steel framework, installing new system drainage and the continued first fix carpentry and first fix M&E works to the east wing.

For the new entrance this has now allowed us to enable the build up from the basement to ground and roof level.

The east wing has seen great steps, with mechanical, electrical and carpentry first fix currently happening.

What to expect in July

  • Phase 2 steel framework build up
  • Continued drainage system to new entrance
  • Continuation of first fix on east wing all floors
  • Soft landscape work commencing again with external light services

If you have any queries about the works being carried out please speak to Site Manager, Sergiu on 07977 165 330.


To view the full resident newsletter for June, please click here.