The Equans site team would like to thank you for your patience and understanding during our construction works on this scheme. We will be closing the site over the festive period from Thursday 22nd December and re-opening Tuesday 3rd January 2023. If you see any unauthorised people trying to access our site during this period, please call the Police immediately.

From all of us at Equans we wish you a Merry Christmas and a happy new year.

Site update

Since our last update, we have completed the isolation of all services in east wing properties (5th floor to ground) and we are currently working through the planned demolition process which is nearly complete.

We are currently working through structural, mechanical and electrical investigations once areas are exposed.

We are also finalising refurbishment of the east wing bell tower, doing the final touches with lead installation on the turret.

In the new year we will be starting the demolition of the old entrance bridge and the new entrance extension.

What's next?

In January and February 2023 we will complete all associated demolition works and start the construction of your soon to be new east wing.