Works update


Cowen Avenue works update

Block A (1-14): All vents and rainwater goods have been replaced and the balcony walkways and balustrades are fitted. Panels for the private balconies are ready to be fitted and will be completed by February. All electrical testing is complete and the new light fittings will be replaced as the new soffits are fitted over the next couple of weeks. Concrete repairs have started and will be complete by the end of January, along with the top coat of paint on the rear of the block.

Block B (15-28): All balconies and balustrades are fitted and will have finishes done by the end of January. The majority of concrete repairs are complete done and will be complete by the end of the month. The grid soffit system has been fitted and all electrical testing is complete.

Block C(29-46): All balconies and balustrades are fitted and will have finishes done by the end of January. Corner panels and repairs are currently being undertaken, while the private balcony quote is underway. Works are due to complete at the end of the month.

Works to all blocks:

Extra bins will be added to the new bin shelter at the end of Block 3.

All blocks will receive a full clean-down following the rendering works.

Handovers will be undertaken property by property, as they complete.

Keep a look out for the date of our next Resident Engagement Day!

Please remember, if you have any questions regarding the works, your first point of contact is your Resident Liaison Officer (RLO).