Key Dates
Next Tarmac Visit
The next tarmac visit is due on 31st January 2020 to complete all the outstanding roads.
First Timer Frame Erection
This timber frame erection process will continue for 15 months until completion.
Next Tarmac Visit
We are well underway
with the drainage and ground floor slabs to phase 2 and are planning the next
tarmac visit for the end of November, week commencing 25th November, which will give us a clean site coming
into the harder winter months.
Meet the Contractor
It is a chance for the local community to come and meet ENGIE and ask any questions they may have ahead of the new development commencing.